Imagine asking a delivery team a simple question:
“When will this be done?”
After a short discussion, someone replies:
“Five Sprints.”
It sounds precise, it sounds reassuring, it sounds like control. But complex work rarely behaves that neatly. The problem is not that teams are careless or that they are poor at estimating; the problem is that delivery contains variation.
Work differs, dependencies appear, some items flow quickly, others do not. So a single-point forecast often gives the appearance of certainty while hiding the uncertainty that matters most.
Probabilistic forecasting takes a different approach.
Instead of asking:
“What is the date?”
It asks:
“What is likely?”
That shift matters for both Scrum and Kanban teams.
What Probabilistic Forecasting Really Means
Probabilistic forecasting does not need advanced maths.
At its core, it means:
Using historical delivery data
Recognising variation
Expressing forecasts as likelihoods
Making uncertainty visible rather than pretending it is not there
For Kanban-oriented teams, this often starts with lead time; for Scrum teams, it often starts with velocity or story count. The mechanics differ slightly, but the thinking is the same.
Probabalistic Forecasting in a Kanban Context: Using Lead Time
In the Kanban Method, one of the core flow metrics is lead time, how long it takes for a work item to move from commitment to completion. Many teams calculate an average lead time and stop there. That is usually where the misunderstanding begins.
The Average Is Not the Forecast
Imagine a team’s average lead time is 8 days. This does not mean the next item will take 8 days. What matters more is the spread of results across similar completed items.
If, for a given work item type, the data shows:
50% of items are completed within 7 days
85% of items are completed within 12 days
95% of items are completed within 18 days
Then the forecast becomes:
- There is a 50% likelihood we will complete the next item within 7 days
- There is an 85% likelihood we will complete the next item within 12 days
- There is a 95% likelihood we will complete the next item within 18 days
That is far more useful than saying “the average is 8 days”. It shows likelihood, makes risk visible, and it gives stakeholders a more honest basis for decisions.
Work Item Types Matter
Not all work behaves the same.
If you mix:
Defects
Small enhancements
Larger feature work
into one dataset, the forecast becomes blurred. Lead time forecasting becomes much more meaningful when you forecast by work item type.
For example:
Standard defects may be completed within 5 days at 85% likelihood
Feature work may be completed within 15 days at 85% likelihood
Now the forecast reflects how work actually flows.
If you want to learn more, why not consider attending my Certified Team Kanban Practitioner or Certified Kanban System Design Training.
Probabilistic Forecasting in Scrum
Scrum teams tend to approach forecasting through Sprint-based completion data.
Two common measures appear:
Velocity — story points completed per Sprint
Story count — items completed per Sprint
Both can support probabilistic forecasting when treated as distributions, not fixed numbers.
Probabilistic Forecasting Using Velocity
Velocity is simply the amount of work completed in a Sprint, often measured in story points.
The Scrum Guide (2020) does not prescribe velocity as a required measure; in fact, it does not mention it at all, but many Scrum teams track it as part of understanding delivery patterns over time. The problem comes when velocity is treated as a single fixed number.
Imagine the last eight Sprints produced:
28, 34, 31, 36, 29, 33, 30, 35 story points completed per Sprint.
Instead of turning that into one average and pretending it is stable, we can look at the distribution.
For example:
50% of Sprints delivered 32 points or fewer
85% of Sprints delivered 35 points or fewer (Actual number is 34.95)
95% of Sprints delivered 36 points or fewer (Actual number is 35.65)
Now, imagine there are 150 points of similar remaining work.
The forecast can be expressed like this:
We are 50% confident the remaining work will take no more than 5 Sprints
We are 85% confident the remaining work will take no more than 6 Sprints
We are 95% confident the remaining work will take no more than 7 Sprints
Now the forecast becomes a decision tool rather than a promise. That is a much healthier conversation.
From Velocity to Story Count
Instead of asking only:
“How many story points do we complete per Sprint?”
We can also ask:
“How many items do we typically finish per Sprint?”
Imagine a team completed the following number of items across eight Sprints:
6, 12, 9, 14, 8, 11, 7 and 13 stories.
Instead of collapsing this into a single average, we can look at the distribution of outcomes.
For example:
50% of Sprints delivered about 10 stories or fewer
85% of Sprints delivered about 13 stories or fewer
95% of Sprints delivered about 14 stories or fewer
Now, imagine 50 similar items remain.
The forecast becomes:
- 50% likelihood we will deliver the remaining work in about 5 Sprints
- 85% likelihood we will deliver the remaining work in about 6 Sprints
- 95% likelihood we will deliver the remaining work in about 7 Sprints
This is still probabilistic forecasting; it simply uses completed item count rather than points.
The goal is not false precision; it is understanding how the system actually behaves.
If you want to learn how to conduct probabilistic forecasting in Scrum using Velocity or Story count, then consider attending my dual-certified Scrum Better with Kanban training.
The Real Shift: From Certainty to Decision-Making
Probabilistic forecasting is not about becoming statistically sophisticated it is about making better decisions under uncertainty.
Instead of asking:
“When exactly will this be done?”
We ask:
What is the likelihood of finishing by this date?
What confidence level do we need?
What would improve the odds?
That changes the conversation.
Now teams and stakeholders can explore trade-offs such as:
Reducing scope
Splitting work smaller
Improving flow
Stabilising the system
Limiting work in progress
This connects directly to Lean and Agile thinking around flow, empiricism, and managing variability
Why This is Important for You, Your Team and Your Organisation
Deterministic forecasts create the illusion of certainty; probabilistic forecasts create informed choices.
Kanban gives us lead time and flow visibility, Scrum gives us cadence and regular inspection. Both support empiricism, and both become more useful when we stop pretending complex work can be predicted with a single number.
Forecasting is not about predicting the future with certainty; it is about understanding your system well enough to make better decisions within it.